NEC Article 250 governs how a service is grounded and bonded, and inspectors check it closely. This generator turns your service details into a printable checklist of the specific connections required, with the grounding electrode conductor and bonding jumpers sized straight from the NEC tables.
How it works
Two NEC tables drive the conductor sizing. The grounding electrode conductor comes from Table 250.66 indexed by the largest ungrounded service conductor, and equipment bonding jumpers come from the same table for the supply side. The tool applies these rules:
GEC size ← Table 250.66 (by largest service conductor)
to ground rods ← never larger than 6 AWG copper (250.66(A))
main bonding ← main service only; subpanels keep neutral and ground separate
electrodes ← all present electrodes must be bonded together (250.50)
Based on the panel type it includes either a main bonding jumper (service) or separated neutral and ground buses plus a feeder equipment grounding conductor (subpanel), then lists every electrode and bonding connection you have to make.
Worked example: 200 A residential service
Consider a typical single-family home with a 200 A main panel, 2/0 AWG copper service-entrance conductors, a pair of ground rods, a metal water pipe entering from the street, and a poured concrete foundation:
| Item | Rule | Sizing / requirement |
|---|---|---|
| Grounding electrode conductor (GEC) | Table 250.66 | 4 AWG copper (for 2/0 service) |
| GEC tap to each ground rod | NEC 250.66(A) | 6 AWG copper maximum |
| Ground rods | NEC 250.53(A)(2) | Two rods at least 6 ft apart if not 25 Ω |
| Metal water pipe bond | NEC 250.104 | 4 AWG copper (same as GEC) |
| Concrete-encased electrode | NEC 250.52(A)(3) | Must be used if present, 20 ft of 1/2-in rebar or 2 AWG wire |
| Main bonding jumper | NEC 250.28 | Required at main service; remove at subpanel |
All electrodes — rods, water pipe, and the Ufer ground — must be bonded together into a single grounding electrode system per NEC 250.50.
Service vs. subpanel: the critical difference
At the main service the grounded neutral and the equipment ground share the same bus through the main bonding jumper. At a subpanel (any panel fed from another panel) these must be kept entirely separate: the neutral bus is isolated from the enclosure, a separate ground bus bonds to the enclosure, and the feeder must carry a fourth wire — the equipment grounding conductor — back to the main panel. Leaving the neutral and ground bonded at a subpanel creates parallel neutral return paths, a shock hazard and a code violation.
Common inspection failures
- Ground rods driven fewer than 8 ft deep (NEC 250.53(B) requires full 8 ft unless rock is encountered).
- Metal water pipe bond run to the wrong side of the water meter — it must be to the street side, or both sides must be bonded.
- Forgetting the intersystem bonding termination (NEC 250.94) for cable TV, telephone and solar system grounds.
- Subpanel neutral and ground tied on the same bar — the most common subpanel deficiency on inspection.
Always confirm conductor sizing and electrode requirements against the specific NEC edition adopted by your local authority having jurisdiction, as some jurisdictions amend Article 250.