Earthwork Swell & Shrinkage Calculator

Convert bank, loose, and compacted soil volumes using swell and shrinkage

Converts between bank (in-place), loose (truck), and compacted soil volumes using swell and shrinkage factors for common soil types. Enter a volume in any of the three states to get the other two, plus an estimate of truck loads needed to haul the loose material away. It runs free in your browser on Gera Tools, with nothing uploaded.

Last updated Source: Gera Tools

What is swell?

When you excavate soil it loosens and takes up more space than it did in the ground. Swell is that increase. A swell of 25 percent means 100 cubic yards of bank material becomes 125 cubic yards loose in the truck. The load factor is 1 divided by (1 plus swell).

Soil changes volume three times during earthwork: in the ground (bank), in the truck (loose, swelled), and placed as fill (compacted, shrunk). Mixing up these states is one of the most common and costly errors in earthwork bidding and scheduling. This calculator converts cleanly between all three and estimates the number of truck loads to haul the loose material.

How it works

loose     = bank × (1 + swell)
compacted = bank × (1 − shrinkage)
bank      = loose / (1 + swell)   = compacted / (1 − shrinkage)
truck loads = ceil(loose volume / truck capacity)

Swell and shrinkage are independent soil properties: swell acts when you excavate, shrinkage acts when you compact. A single cubic yard of bank clay can swell to 1.25 yd³ loose in the truck and shrink back to only 0.88 yd³ compacted fill. Both transformations can be true simultaneously.

Worked example

100 yd³ bank excavation of common clay (25% swell, 12% shrinkage):

  • Loose volume = 100 × 1.25 = 125 yd³ → ceil(125 / 20) = 7 truck loads (20 yd³ truck)
  • Compacted fill = 100 × (1 − 0.12) = 88 yd³

Reverse question: You need 100 yd³ of compacted clay fill. How much bank material must you excavate?

  • Bank needed = 100 / (1 − 0.12) = 100 / 0.88 = 113.6 yd³

If you excavate only 100 yd³ bank, you end up with only 88 yd³ of compacted fill — 12 yd³ short. This is the calculation that catches out many first-time earthwork estimates.

Typical swell and shrinkage factors

MaterialSwell %Shrinkage %Notes
Sandy soil~10–15%~5–8%Low swell; compacts well
Common clay~20–30%~10–15%Most variable; test before bidding
Gravel~10–12%~2–5%Predictable; granular material
Topsoil~20–25%~10–12%Organic content affects compaction
Soft rock / shale~30–40%~5–10%Breaks down on excavation
Hard rock~50–80%~0%Volume mostly increases; doesn’t shrink as fill

These are typical mid-range values from earthwork references. Always use soil-specific test data for any real contract or bid — site-specific factors can differ substantially from these defaults.

Why these numbers matter for bidding

Under-counting loose volume means you order too few trucks and the job stalls mid-excavation waiting for more haulage.

Under-counting bank material needed for fill means you run out of cut material before achieving design grade and must import expensive borrow.

Over-counting compacted yield inflates the apparent fill coverage, causing grade deficits that require rework and import.

A consistent rule: always think in bank measure (the pay item on most contracts), convert to loose for haulage, and convert to compacted for fill placement — and do those conversions explicitly rather than eyeballing.