One vocabulary across three frameworks
Project management spans several methods — PMBOK, PRINCE2 and Agile — that often describe similar ideas with different words. This reference defines the core terms from each so you can read a plan, a status report or a sprint board and know exactly what is meant. Search by keyword or filter by framework to find the term you need.
Framework overview: what each one emphasises
PMBOK (Project Management Body of Knowledge) is a process-based framework from PMI that organises project management into five process groups (Initiating, Planning, Executing, Monitoring & Controlling, Closing) and ten knowledge areas including scope, schedule, cost, and risk. It is descriptive rather than prescriptive — it defines what good practice looks like without dictating exactly how to apply it. PMP certification is based on PMBOK.
PRINCE2 (PRojects IN Controlled Environments) is a governance-first method developed in the UK. It divides a project into managed stages with defined business-case justification at each gate. A project board makes go/no-go decisions; the project manager works within tolerance boundaries and escalates only when those boundaries would be exceeded. PRINCE2 is particularly common in UK public sector and government projects.
Agile / Scrum takes a completely different approach: rather than planning the full scope upfront, it delivers working product in short iterations (sprints, typically two weeks). Requirements are held in a prioritised backlog and refined as understanding grows. Velocity and burndown replace earned value as progress indicators. Agile is most applicable when requirements are uncertain or will change during delivery.
How it works
Project terms cluster around three jobs: defining scope, tracking progress and controlling change.
Define scope → WBS / product breakdown structure, baseline, milestone
Track progress → critical path, earned value (SPI = EV/PV, CPI = EV/AC), velocity, burndown
Control change → tolerance, exception report, change request, risk register
Earned value links scope and progress numerically: an SPI below 1 means the project is behind schedule, and a CPI below 1 means it is over budget. PRINCE2 adds governance gates so a project board can stop or redirect work between stages.
Reading earned value numbers
Earned value management (EVM) gives three numbers that, together, show where a project stands:
- PV (Planned Value) — the budgeted cost of the work you planned to have done by this point.
- EV (Earned Value) — the budgeted cost of the work actually completed.
- AC (Actual Cost) — what you actually spent on the work completed.
From those three: SPI = EV ÷ PV (a ratio below 1 means behind schedule) and CPI = EV ÷ AC (a ratio below 1 means over budget). Tracking SPI and CPI as a trend — not a single snapshot — is what makes them genuinely useful: a project trending from 0.9 to 0.85 to 0.78 needs a recovery plan faster than one holding steady at 0.92.
Tips and notes
A task on the critical path has zero float — protect those tasks first when resources are tight. PRINCE2 tolerance defines how far a stage can drift before it must escalate; set it deliberately so the board is not flooded with exception reports on minor variances. Agile velocity is a planning aid, not a productivity score — comparing teams by velocity is meaningless because story points are relative to each team’s own calibration.